CSIT214-Lab 4 Solved

Task 1: (Verbal progress report for the project) – 3 minutes per group

·       One member from each group presents the progress of their group

o   Use 1-2 slides

o   Introduce their group members and their roles.

o   Report on progress and plans for the remaining of the project.

 

Task 2:

 

Create a precedence activity network using the following details. You can draw this on paper or use a tool of your choice.

 

Activity
Depends on
Duration

(days)
A
 
5
B
A
7
C
B
6
D
A
5
E
D
10
F
B
15
G
B
8
H
G
8
I
C
4
J
G
4
K
E,F
5
L
I,H
3
 

Calculate the earliest and latest start and end dates and the float associated with each activity. From this identify the critical path.