1. Introduction
You are hired by a startup company who is considering to use cloud computing instead of building its own infrastructure. There is concensus that a cloud computing software stack at the layer of IaaS will be used, but its not clear whether the computing resources should be rented from a public cloud on-demand, or whether a private cloud should be purchased. You are tasked to find the cost breakdown of a private cloud, and compare that to what Amazon would charge. You can find many instance types defined at http://aws.amazon.com/ec2/instance-types/, and their prices are set at http://aws.amazon.com/ec2/pricing/. For pricing purposes, please stick to Linux ondemand pricing.
Since you have to estimate the cost of the hardware when building a private cloud, you can use hardware prices found at ThinkMate website (https://www.thinkmate.com) as good sources for server hardware. You must include a printout of your shoping cart in your final writeup report for this assignment; include this as an appendix at the end of your report.
You are to estimate the cost of different configurations for 3 different set of requirements:
• Configuration 1: Hadoop/Spark Cluster with 256K-cores, 2PB memory, 400PB HDD, and 25Gb/s Ethernet Fat-Tree network (each VM should be equivalent to the d2.8xlarge instance); in addition to the compute resources, a 800PB distributed storage shared across the entire cloud should be procured, with enough capacity for 800GB/sec throughput (for pricing comparison, see S3)
• Configuration 2: Support 1M virtual machines (VM) where each VM requires 2-core, 16GB RAM, 75GB NVMe storage, and 10Gb/s Fat-Tree network (each VM should be equivalent to the r5d.large instances); in addition to the compute resources, a 10PB distributed storage shared across the entire cloud should be procured, with enough capacity for 100GB/sec throughput (for pricing comparison, see S3)
• Configuration 3: Support deep learning with 1 exaflop of double precision performance (hint: each VM should be equivalent to p3.16xlarge instances; you will want to use the NVIDIA V100 GPUs (8 GPUs per node), and allocate 8-cores per GPU (64-cores per node) with 8GB of memory per core (512GB per node); the network to use is at least 10Gb/s per GPU (100Gb/s should work), and should be organized in a Fat-Tree network; in addition to the compute resources, a 1PB distributed storage shared across the entire cloud should be procured, with enough capacity for 10GB/sec throughput (for pricing comparison, see S3)
2. What you will submit?
Your deliverables for this project are to be written in a report, which will include the following:
• Report: A written document (typed, named hw4-report.pdf) describing your answers to the above questions.
o you will have to factor in things other than hardware, such as cooling, power, administration costs, network infrastructure (e.g. switches); you can assume 1 system administrator is needed for every
1000 servers o show your data in three different tables with the costs of each of the 3 configurations, broken down by components (e.g. servers, network switches, cables, racks, cooling, power, administration, etc)
o summarize your data in a 4th table, comparing the public cloud cost to the private cloud cost
• Explain in words if it is better to rent or buy. If it is better to buy, what utilization must you maintain over the 5 year lifetime of the private cloud in order to break even on the investment?
• Include your shopping cart of the 3 configurations. Your submission should be a single large PDF file, starting with your report, and followed by the shopping carts.
Table 1: Table summarizing each of the three configurations; please include 1 table per configuration, for a total of 3 tables
Description Price per Item Quantity Total Price
Compute Servers
Network Switches
Network Cables
Racks
Storage Servers
Electric Power
Cooling
Administration
TOTAL N/A N/A N/A
Table : Summary table comparing the 3 configurations between the public and private cloud; your cost of power, cooling, and administration should be to cover 5 years of costs
Configuration 1 Configuration 2 Configuration 3
Public Cloud (including EC2 and S3) Cost over 5 years, 24/7 operation, with 100% usage
Private Cloud cost over 5 years, 24/7 operation, with 100% usage
What utilization must be achieved with the private cloud to make the private cloud option more attractive than the public cloud?
Submit code/report through GIT. If you cannot access your repository contact the TAs. You can find a git cheat sheet here: https://www.git-tower.com/blog/git-cheat-sheet/ Grades for late programs will be lowered 10% per day late.